Nov 26, 2022After Engineering technician’s hardworking, we finished 4 channels 40G and 4channels 16G FC 80KM DWDM transmission, and this DWDM System supports 1+1 hot backup.
|
After 24 hours of continuous flow data test, the DWDM System is working good. We completed this project, and delivered to customers for use
.
DWDM System in Disaster recovery backup transmission network application:
DWDM System in Disaster recovery backup transmission network application
Solution Highlights:
1. The most comprehensive IP and SAN service interface, supporting almost all IP and SAN services at present;
2. The disaster recovery range canexpand to 130km to meet the large-capacity disaster recovery requirements of multiple physical nodes;
3)DWDM hardware, line 1+1 backup protection, to achieve the highest level of network protection.